Select Year

Select Month

October 2024

Brigade Nanda Heights as on October '24

Brigade Nanda Heights

Brigade Nanda Heights : Finishing Works as on October '24

Brigade Nanda Heights : Finishing Works

Brigade Nanda Heights : Finishing Works as on October '24

Brigade Nanda Heights : Finishing Works

Brigade Nanda Heights : Common Area Finishing Works. Entry portal & Basement VDF flooring as on October '24

Brigade Nanda Heights : Common Area Finishing Works. Entry portal & Basement VDF flooring

Brigade Nanda Heights : Milestone Release On Commencement of Flooring 18th to 23rd Floor as on October '24

Brigade Nanda Heights : Milestone Release On Commencement of Flooring 18th to 23rd Floor

Brigade Nanda Heights : Milestone Release On Commencement of Flooring 18th to 23rd Floor as on October '24

Brigade Nanda Heights : Milestone Release On Commencement of Flooring 18th to 23rd Floor

September 2024

Brigade Nanda Heights as on September '24

Brigade Nanda Heights

Brigade Nanda Heights : Finishing Works as on September '24

Brigade Nanda Heights : Finishing Works

Brigade Nanda Heights : Finishing Works as on September '24

Brigade Nanda Heights : Finishing Works

Brigade Nanda Heights : Finishing Works as on September '24

Brigade Nanda Heights : Finishing Works

Brigade Nanda Heights : Common Area Finishing Works as on September '24

Brigade Nanda Heights : Common Area Finishing Works

August 2024

Brigade Nanda Heights as on August '24

Brigade Nanda Heights

Brigade Nanda Heights : Finishing Works as on August '24

Brigade Nanda Heights : Finishing Works

Brigade Nanda Heights : Finishing Works as on August '24

Brigade Nanda Heights : Finishing Works

Brigade Nanda Heights : Finishing Works as on August '24

Brigade Nanda Heights : Finishing Works

Brigade Nanda Heights : Common Area Finishing Works as on August '24

Brigade Nanda Heights : Common Area Finishing Works

July 2024

Brigade Nanda Heights : Milestone Release On Commencement of Installation of Lifts as on July '24

Brigade Nanda Heights : Milestone Release On Commencement of Installation of Lifts

Brigade Nanda Heights : Finishing Works as on July '24

Brigade Nanda Heights : Finishing Works

Brigade Nanda Heights : Finishing Works as on July '24

Brigade Nanda Heights : Finishing Works

Brigade Nanda Heights : Finishing Works as on July '24

Brigade Nanda Heights : Finishing Works

Brigade Nanda Heights : Common Area Finishing Works as on July '24

Brigade Nanda Heights : Common Area Finishing Works

Brigade Nanda Heights : Common Area Finishing Works as on July '24

Brigade Nanda Heights : Common Area Finishing Works

Brigade Nanda Heights : Common Area Finishing Works as on July '24

Brigade Nanda Heights : Common Area Finishing Works

June 2024

Brigade Nanda Heights : Terrace slab completed. Above terrace works are in progress as on June '24

Brigade Nanda Heights : Terrace slab completed. Above terrace works are in progress

Brigade Nanda Heights : Finishing Works as on June '24

Brigade Nanda Heights : Finishing Works

Brigade Nanda Heights : Finishing Works as on June '24

Brigade Nanda Heights : Finishing Works

Brigade Nanda Heights : Finishing Works as on June '24

Brigade Nanda Heights : Finishing Works

Brigade Nanda Heights : Common Area Finishing Works as on June '24

Brigade Nanda Heights : Common Area Finishing Works

May 2024

Brigade Nanda Heights : Finishing Works as on May '24

Brigade Nanda Heights : Finishing Works

Brigade Nanda Heights : Finishing Works as on May '24

Brigade Nanda Heights : Finishing Works

Brigade Nanda Heights : Finishing Works as on May '24

Brigade Nanda Heights : Finishing Works

Brigade Nanda Heights : Finishing Works as on May '24

Brigade Nanda Heights : Finishing Works

Brigade Nanda Heights : Milestone Release On commencement of Painting GF to 8th Floor as on May '24

Brigade Nanda Heights : Milestone Release On commencement of Painting GF to 8th Floor

Brigade Nanda Heights : Milestone Release On commencement of Painting GF to 8th Floor as on May '24

Brigade Nanda Heights : Milestone Release On commencement of Painting GF to 8th Floor

Brigade Nanda Heights : Milestone Release On commencement of Painting GF to 8th Floor as on May '24

Brigade Nanda Heights : Milestone Release On commencement of Painting GF to 8th Floor

April 2024

Brigade Nanda Heights : Finishing Works as on April '24

Brigade Nanda Heights : Finishing Works

Brigade Nanda Heights : Finishing Works as on April '24

Brigade Nanda Heights : Finishing Works

Brigade Nanda Heights : Finishing Works as on April '24

Brigade Nanda Heights : Finishing Works

Brigade Nanda Heights : Finishing Works as on April '24

Brigade Nanda Heights : Finishing Works

Brigade Nanda Heights : Terrace slab completed, Above terrace works are in progress as on April '24

Brigade Nanda Heights : Terrace slab completed, Above terrace works are in progress

Brigade Nanda Heights : Milestone Release on commencement of Fixing of Doors & Windows Ground to 8th Floor as on April '24

Brigade Nanda Heights : Milestone Release on commencement of Fixing of Doors & Windows Ground to 8th Floor

Brigade Nanda Heights : Milestone Release on commencement of Fixing of Doors & Windows Ground to 8th Floor as on April '24

Brigade Nanda Heights : Milestone Release on commencement of Fixing of Doors & Windows Ground to 8th Floor

March 2024

Brigade Nanda Heights : Finishing Works as on March '24

Brigade Nanda Heights : Finishing Works

Brigade Nanda Heights : Finishing Works as on March '24

Brigade Nanda Heights : Finishing Works

Brigade Nanda Heights : Finishing Works as on March '24

Brigade Nanda Heights : Finishing Works

Brigade Nanda Heights : Structure 23rd floor completed, and Above terrace works are in progress as on March '24

Brigade Nanda Heights : Structure 23rd floor completed, and Above terrace works are in progress

February 2024

Brigade Nanda Heights : Milestone Release On Casting of Terrace slab as on February '24

Brigade Nanda Heights : Milestone Release On Casting of Terrace slab

Brigade Nanda Heights : Structure 23rd floor completed. Terrace floor slab works are in progress as on February '24

Brigade Nanda Heights : Structure 23rd floor completed. Terrace floor slab works are in progress

Brigade Nanda Heights : Finishing Works as on February '24

Brigade Nanda Heights : Finishing Works

Brigade Nanda Heights : Finishing Works as on February '24

Brigade Nanda Heights : Finishing Works

January 2024

Brigade Nanda Heights : Structure 22nd floor completed. 23rd floor slab works are in progress as on January '24

Brigade Nanda Heights : Structure 22nd floor completed. 23rd floor slab works are in progress

Brigade Nanda Heights : Finishing Works as on January '24

Brigade Nanda Heights : Finishing Works

Brigade Nanda Heights : Finishing Works as on January '24

Brigade Nanda Heights : Finishing Works

Brigade Nanda Heights : Milestone Release On Casting of 21st Floor as on January '24

Brigade Nanda Heights : Milestone Release On Casting of 21st Floor

December 2023

Brigade Nanda Heights :  Structure 20th floor completed. 21st floor slab works are in progress as on December '23

Brigade Nanda Heights : Structure 20th floor completed. 21st floor slab works are in progress

Brigade Nanda Heights : Water proofing works up to 8th  floor completed 9th floor works are in progress as on December '23

Brigade Nanda Heights : Water proofing works up to 8th floor completed 9th floor works are in progress

Brigade Nanda Heights : Tiling works up to 3rd floor work in progress as on December '23

Brigade Nanda Heights : Tiling works up to 3rd floor work in progress

November 2023

Brigade Nanda Heights : Milestone Release – On Casting of Eighteenth Floor Slab as on November '23

Brigade Nanda Heights : Milestone Release – On Casting of Eighteenth Floor Slab

Brigade Nanda Heights : Finishing Works. Water proofing works up to 6th floor completed 7th floor works are in progress as on November '23

Brigade Nanda Heights : Finishing Works. Water proofing works up to 6th floor completed 7th floor works are in progress

Brigade Nanda Heights : Finishing Works. Tiling works commenced and entire 2nd floor completed as on November '23

Brigade Nanda Heights : Finishing Works. Tiling works commenced and entire 2nd floor completed

October 2023

Brigade Nanda Heights : Structure 16th floor completed 17th floor work in progress as on October '23

Brigade Nanda Heights : Structure 16th floor completed 17th floor work in progress

Brigade Nanda Heights : Water proofing works up to 5th floor completed 6th floor work in progress as on October '23

Brigade Nanda Heights : Water proofing works up to 5th floor completed 6th floor work in progress

September 2023

Brigade Nanda Heights : View from South Side (14th floor slab 100% completed 15th floor slab work in progress) as on September '23

Brigade Nanda Heights : View from South Side (14th floor slab 100% completed 15th floor slab work in progress)

Brigade Nanda Heights : Water proofing works up to 4th floor completed 5th floor work in progress as on September '23

Brigade Nanda Heights : Water proofing works up to 4th floor completed 5th floor work in progress

Brigade Nanda Heights : Milestone Release On Casting of Fourteenth floor slab as on September '23

Brigade Nanda Heights : Milestone Release On Casting of Fourteenth floor slab

August 2023

Brigade Nanda Heights Tower A : View From North Side (11th floor 100% completed 12th floor work in progress) as on August '23

Brigade Nanda Heights Tower A : View From North Side (11th floor 100% completed 12th floor work in progress)

Brigade Nanda Heights Tower A : Finishing Works and Water proofing works in progress up to 2nd floor as on August '23

Brigade Nanda Heights Tower A : Finishing Works and Water proofing works in progress up to 2nd floor

Brigade Nanda Heights : Milestone Release – On Casting of 9th Floor Slab as on August '23

Brigade Nanda Heights : Milestone Release – On Casting of 9th Floor Slab

July 2023

Brigade Nanda Heights Tower A : View From North Side (8th Floor 100% Completed 9th Floor work in progress) as on July '23

Brigade Nanda Heights Tower A : View From North Side (8th Floor 100% Completed 9th Floor work in progress)

Brigade Nanda Heights Tower A Structure : View From South Side (8th Floor Completed, 9th Floor work in progress) as on July '23

Brigade Nanda Heights Tower A Structure : View From South Side (8th Floor Completed, 9th Floor work in progress)

Brigade Nanda Heights Tower A : Finishing Works. And Water proofing works in progress up to 2nd floor as on July '23

Brigade Nanda Heights Tower A : Finishing Works. And Water proofing works in progress up to 2nd floor

June 2023

Brigade Nanda Heights Tower A : View From North Side (6th floor 100% completed. 7th floor work in progress) as on June '23

Brigade Nanda Heights Tower A : View From North Side (6th floor 100% completed. 7th floor work in progress)

Brigade Nanda Heights Tower A : View From South Side (6th floor completed, 7th floor work in progress) as on June '23

Brigade Nanda Heights Tower A : View From South Side (6th floor completed, 7th floor work in progress)

Brigade Nanda Heights Tower A : Finishing Works. Water proofing works in progress up to 2nd floor as on June '23

Brigade Nanda Heights Tower A : Finishing Works. Water proofing works in progress up to 2nd floor

Brigade Nanda Heights : Milestone Release – On Casting of 5th Floor Slab as on June '23

Brigade Nanda Heights : Milestone Release – On Casting of 5th Floor Slab

May 2023

Brigade Nanda Heights Tower A (view from North side) : 4th floor slab concreting 100% completed & 5th floor works are in progress as on May '23

Brigade Nanda Heights Tower A (view from North side) : 4th floor slab concreting 100% completed & 5th floor works are in progress

Brigade Nanda Heights Tower A (view from East side) : 4th floor slab 100 % concreting works completed & 5th floor works are in progress as on May '23

Brigade Nanda Heights Tower A (view from East side) : 4th floor slab 100 % concreting works completed & 5th floor works are in progress

Brigade Nanda Heights Tower A (view from  South side) : 4th floor slab conreting 100% completed & 5th floor works are in progress as on May '23

Brigade Nanda Heights Tower A (view from South side) : 4th floor slab conreting 100% completed & 5th floor works are in progress

Brigade Nanda Heights Tower A (view from west side) : 4th floor slab 100% concreting completed and 5th floor works are in progress as on May '23

Brigade Nanda Heights Tower A (view from west side) : 4th floor slab 100% concreting completed and 5th floor works are in progress

Brigade Nanda Heights Tower A (view from top) : 4th floor slab conreting 100% completed & 5th floor works are in progress as on May '23

Brigade Nanda Heights Tower A (view from top) : 4th floor slab conreting 100% completed & 5th floor works are in progress

April 2023

Brigade Nanda Heights Tower A (view from North side) : 2nd floor slab concreting 100% completed & 3rd floor works are in progress as on April '23

Brigade Nanda Heights Tower A (view from North side) : 2nd floor slab concreting 100% completed & 3rd floor works are in progress

Brigade Nanda Heights Tower A (view from East side) : 2nd floor slab 100% concreting works completed & 3rd floor works are in progress as on April '23

Brigade Nanda Heights Tower A (view from East side) : 2nd floor slab 100% concreting works completed & 3rd floor works are in progress

Brigade Nanda Heights Tower A (view from  South side) : 2nd floor slab conreting 100% completed & 3rd floor works are in progress as on April '23

Brigade Nanda Heights Tower A (view from South side) : 2nd floor slab conreting 100% completed & 3rd floor works are in progress

Brigade Nanda Heights Tower A (view from west side) : 2nd floor slab 100% concreting completed and 3rd floor works are in progress as on April '23

Brigade Nanda Heights Tower A (view from west side) : 2nd floor slab 100% concreting completed and 3rd floor works are in progress

Brigade Nanda Heights Tower A (view from top) : 2nd floor slab conreting 100% completed & 3rd floor works are in progress as on April '23

Brigade Nanda Heights Tower A (view from top) : 2nd floor slab conreting 100% completed & 3rd floor works are in progress

March 2023

Brigade Nanda Heights Tower A (view from North side) : First floor slab concreting completed & podium slab concreting in progress as on March '23

Brigade Nanda Heights Tower A (view from North side) : First floor slab concreting completed & podium slab concreting in progress

Brigade Nanda Heights Tower A (view from  South side) : First floor slab conreting completed & 2nd floor works are in progress as on March '23

Brigade Nanda Heights Tower A (view from South side) : First floor slab conreting completed & 2nd floor works are in progress

Brigade Nanda Heights Tower A (view from East side) : First floor slab concreting works are completed & 2nd floor works are in progress  as on March '23

Brigade Nanda Heights Tower A (view from East side) : First floor slab concreting works are completed & 2nd floor works are in progress

Brigade Nanda Heights Tower A (view from west side): First floor slab concreting completed and 2nd floor works are in progress as on March '23

Brigade Nanda Heights Tower A (view from west side): First floor slab concreting completed and 2nd floor works are in progress

Brigade Nanda Heights Tower A: Milestone Release – On Casting of Ground Floor Slab as on March '23

Brigade Nanda Heights Tower A: Milestone Release – On Casting of Ground Floor Slab

February 2023

Brigade Nanda Heights Tower A (view from North side) : Ground floor works completed. Podium slab works are in progress as on February '23

Brigade Nanda Heights Tower A (view from North side) : Ground floor works completed. Podium slab works are in progress

Brigade Nanda Heights Tower A (view from East side) : Ground floor works completed & ready for concreting. Podium slab works are in progress  as on February '23

Brigade Nanda Heights Tower A (view from East side) : Ground floor works completed & ready for concreting. Podium slab works are in progress

Brigade Nanda Heights Tower A (view from  South side) : Ground floor works completed & ready for concreting as on February '23

Brigade Nanda Heights Tower A (view from South side) : Ground floor works completed & ready for concreting

Brigade Nanda Heights Tower A (view from west side) : Ground floor works completed and ready for concreting as on February '23

Brigade Nanda Heights Tower A (view from west side) : Ground floor works completed and ready for concreting

January 2023

Brigade Nanda Heights Tower A (view from North side) : Upper basement completed. Ground floor works are in progress as on January '23

Brigade Nanda Heights Tower A (view from North side) : Upper basement completed. Ground floor works are in progress

Brigade Nanda Heights Tower A (view from top) : Upper basement completed. Ground floor works are in progress as on January '23

Brigade Nanda Heights Tower A (view from top) : Upper basement completed. Ground floor works are in progress

Brigade Nanda Heights Tower A (view from East side) : Upper basement completed. Ground floor works are in progress as on January '23

Brigade Nanda Heights Tower A (view from East side) : Upper basement completed. Ground floor works are in progress

Brigade Nanda Heights Tower A (view from west side) : Upper basement completed. Ground floor sworks are in progress as on January '23

Brigade Nanda Heights Tower A (view from west side) : Upper basement completed. Ground floor sworks are in progress

October 2022

Brigade Nanda Heights : Milestone Release - On Casting of Footing/Raft as on October '22

Brigade Nanda Heights : Milestone Release - On Casting of Footing/Raft

Brigade Nanda Heights Tower A (view from North side) : Basement raft concreting completed & Upper basement slab works are in progress as on October '22

Brigade Nanda Heights Tower A (view from North side) : Basement raft concreting completed & Upper basement slab works are in progress

Brigade Nanda Heights Tower A (view from West side) : Upper basement slab works are in progress as on October '22

Brigade Nanda Heights Tower A (view from West side) : Upper basement slab works are in progress

Brigade Nanda Heights Tower A (view from East side) : Basement raft concreting completed & Upper basement slab works are in progress as on October '22

Brigade Nanda Heights Tower A (view from East side) : Basement raft concreting completed & Upper basement slab works are in progress

Brigade Nanda Heights Tower A (view from top) : Basement raft concreting completed & Upper basement slab works are in progress as on October '22

Brigade Nanda Heights Tower A (view from top) : Basement raft concreting completed & Upper basement slab works are in progress

November 2022

Tower A (view from North side) : Upper basement slab in progress & Ground floor vertical works are in progress as on November '22

Tower A (view from North side) : Upper basement slab in progress & Ground floor vertical works are in progress

Tower A (view from top) : Upper basement slab in progress and Ground floor verticals works are in progress as on November '22

Tower A (view from top) : Upper basement slab in progress and Ground floor verticals works are in progress

Tower A (view from East side): Upper basement slab in progress & Ground floor vertical works are in progress as on November '22

Tower A (view from East side): Upper basement slab in progress & Ground floor vertical works are in progress

Tower A (view from west side) : Upper basement slab in progress & Ground floor vertical works are in progress as on November '22

Tower A (view from west side) : Upper basement slab in progress & Ground floor vertical works are in progress

December 2022

Tower A (view from North side) : Upper basement slab concreting completed. Ground floor slab works are in progress as on December '22

Tower A (view from North side) : Upper basement slab concreting completed. Ground floor slab works are in progress

Tower A (view from top) : Upper basement slab concreting completed. Ground floor slab works are in  progress as on December '22

Tower A (view from top) : Upper basement slab concreting completed. Ground floor slab works are in progress

Tower A (view from East side) : Upper basement slab concreting completed. Ground floor slab works are in progress as on December '22

Tower A (view from East side) : Upper basement slab concreting completed. Ground floor slab works are in progress

Tower A (view from west side) : Upper basement slab concreting completed. Ground floor slab works are in progress as on December '22

Tower A (view from west side) : Upper basement slab concreting completed. Ground floor slab works are in progress

GET IN TOUCH

Write to our team of experts who will ensure you have a truly memorable experience from the simplest queries to elaborate property tours.

Or call us on
080 4647 4062

I Agree to the Terms and Conditions